What a season of maintenance actually looks like

Ten campaigns across five arrays, from November 2025 to August 2026. Blades rebuilt on the turbine, cable pulled inside the transition piece, bolts logged against the design table. Every date below includes the days the weather took.

Fictional wind farms and fictional crews. The work described is the work this trade actually does.

CAMPAIGNSBLADE REPAIRARRAY CABLETORQUE & TENSIONSUBSEA SURVEYWINTER RECOVERYCAMPAIGNSBLADE REPAIRARRAY CABLETORQUE & TENSIONSUBSEA SURVEYWINTER RECOVERYCAMPAIGNSBLADE REPAIRARRAY CABLETORQUE & TENSIONSUBSEA SURVEYWINTER RECOVERY
01
KJELLBANK

Leading edge, rebuilt in place

Category
Blade repair · rope access
Dates
Apr – Aug 2026

Sixty-two blades inspected from ropes, forty-one leading edges rebuilt on the turbine. No jack-up vessel was mobilised for any of them. Median turbine downtime per blade: 2.4 days, weather included.

Campaign lead — M. Røste · Rope access supervisor, IRATA L3 — K. Wojnar · Blade technicians ×8 · Marine coordinator — A. Lindqvist · HSE advisor — P. Duda

02
DUNEWATER

Thirty-one terminations

Category
Array cable · transition piece
Dates
Sep 2025 – Jan 2026

Thirty-one array cable terminations inside the transition piece, including four re-pulls after seabed movement exposed the cable ahead of winter. Every pull logged against the design table.

Campaign lead — J. Halvorsen · Cable jointers ×6 · Survey lead — H. Berg · ROV pilot — T. Bakken · Vessel — CTV, 24 pax

03
HOLM SHOAL

Forty-four flanges, no memory

Category
Torque & tension · foundation
Dates
Jan – Feb 2026

Bolt tension verified on forty-four flange connections between monopile, transition piece and tower. Every value recorded against the design table. Nothing signed off from memory.

Campaign lead — S. Iversen · Bolting technicians ×5 · Quality engineer — N. Kaczmarek · Vessel — SOV, walk-to-work

04
WIDE SANDS

A hundred and twelve kilometres of cable route

Category
Subsea survey · pre-winter
Dates
Nov 2025

One hundred and twelve kilometres of array cable route surveyed before the winter storms. Three sections of exposed cable found, charted and handed to the operator inside the same mobilisation; two were re-covered by a rock placement vessel before the first gale.

Survey lead — E. Mazur · ROV spread ×2 · Data processors ×3 · Client rep on board

05
GREY KNOLL

Nine hours between two storms

Category
Winter recovery · drivetrain
Dates
Feb 2026

Turbine returned to service in a nine-hour window between two depressions. Significant wave height 1.4 m at transfer, 2.6 m six hours later. The window was the whole job.

Campaign lead — M. Røste · Service technicians ×4 · Marine coordinator — A. Lindqvist · Forecast — in-house, 3-hourly

06
TARNBANK

Every turbine, once, before the summer

Category
Inspection · GVI
Dates
Mar – May 2026

General visual inspection of all fifty-eight turbines: tower internals, transition piece, ladders, davits, bolted connections and blade root from the hub. Two hundred and forty findings raised, thirty-one of them ranked for action inside the same season. The array kept turning for the whole campaign; nothing on this scope needs a stop.

Campaign lead — S. Iversen · Inspection technicians ×6 · Quality engineer — N. Kaczmarek · Marine coordinator — A. Lindqvist · Vessel — CTV, 24 pax

07
MARLDEEP

Where the seabed moved

Category
Subsea survey · scour protection
Dates
Jun – Jul 2026

Scour protection surveyed on twenty-six monopiles after a winter of easterlies. Rock cover was found thinned on nine of them and the survey handed over as a charted work list, not as a report. We do not place rock. We tell the operator where it is missing and how much.

Survey lead — E. Mazur · ROV supervisor — D. Feddersen · ROV pilot — T. Bakken · Data processors ×3 · Vessel — workboat, shallow draft

08
WIDE SANDS

Trailing edge, second season

Category
Blade repair · rope access
Dates
May – Jul 2026

Trailing edge bonds opened on nineteen blades, repaired from ropes and closed the same day where the cure allowed it. Eleven repairs are ones we mapped from the survey vessel the winter before, which is why the ropes went up knowing exactly where to stop.

Campaign lead — L. Mikkelsen · Rope access supervisor, IRATA L3 — K. Wojnar · Blade technicians ×6 · HSE advisor — P. Duda · Vessel — CTV, 24 pax

09
DUNEWATER

Reading last winter’s paperwork on the tower

Category
Inspection · post-termination
Dates
Jun 2026

Every one of the thirty-one terminations from the winter campaign re-entered and inspected: seals, hang-off, bend restrictors, earthing. Four J-tube seals replaced. The point of the visit was to check our own work with somebody else’s eyes on it.

Campaign lead — S. Iversen · Inspection technicians ×4 · Quality engineer — R. Ostrowska · Client rep on board · Vessel — CTV, 24 pax

10
GREY KNOLL

Two pulls, one tide

Category
Array cable · re-termination
Dates
Aug 2026

Two array cables re-terminated after an insulation test failed on the second string. Both pulls done inside a single settled spell in August, because the alternative was to leave a string down until spring. Test values went to the operator before the crew came off the tower.

Campaign lead — J. Halvorsen · Cable jointers ×4 · Quality engineer — R. Ostrowska · Marine coordinator — A. Lindqvist · Vessel — SOV, walk-to-work

Sources. Significant wave heights, vessel types (CTV, SOV, walk-to-work, ROV) and the scope of work described are real industry practice — the CTV transfer limit of about 1.50 m significant wave height comes from the 2026 review of CTV transfer safety in Ocean Engineering and from ABPmer. Wind farm names, campaign dates, quantities, crew names and vessel counts are invented for this concept. KELDVIK is not a real company and none of these campaigns took place.